Invest in the future of

sustainable energy!

Join us in supporting the development of

green hydrogen production in Egypt.

Egypt's Hydrogen Strategy
Scale-up in Egypt

Egypt has favorable conditions that foster the development of the Green Hydrogen and can potentially be one of the most competitive places to deliver H2 to Europe

Key Enablers for Hydrogen Scale-up in Egypt
1
Strategic Location
Vast local offtake opportunities and proximity to global markets, particularly Europe, through the main ports on Red Sea and Mediterranean
2
Strong Industrial Base
Strong recent increase of industrial clusters across various industries enables companies at the heart of Hydrogen transformation to prosper
3
High Accessibility
Well-established basic infrastructure in SCZONE
Strategically placed ports with high Green Bunkering potential and good connectivity
Available export infrastructure through potential retrofitting of LNG pipes
4
Renewable Capacity
Ample wind & solar resources favorably positioning Egypt for GH2 production with average wind speeds showing great potential for wind projects
Stakeholders

Upstream

Renewable Power & Interconnection

Egypt has 23 valid MoUs. To date , 15 binding framework agreements have been successfully signed.
Pipeline
Framework Agreements

MoUs
Production Capacity

Renewable Energy Capacity (Solar & Wind) (GW)

38.4
Pilot Phase
72.9
Phase 1

Total111.3

Hydrogen Production Capacity (mn tonnes/ year)

14.9
Pilot Phase
33
Phase 1

Total47.9

Green Fuel Production Capacity (mn tonnes/ year)

10.4
Pilot Phase
20.9
Phase 1

Total31.2

USD 53.9 bn

Pilot Phase Total Investment Cost

USD 118.3 bn

Phase 1 Total Investment Cost

USD 172.2 bn

All Phases: Total Investment

Process Summary
1
Initial Proposal and Project Datasheet
2
Sponsors Assessment and Feedback
3
MoU Signature
4
Land Allocation
5
Preliminary Studies
6
Framework Agreement Signature
7
Pre and Final Feasibility Studies
8
Government Sponsors and Developer FID
9
Project Documents Signature and Financial Close